Hush Villas on Koh Phangan: four pool villas and the team behind them

Project or trading name; a separate legal development company has not been established.

· Projects in the catalogue · 1

Projects in the NovAsia catalogue

Hush Villas is a small, single-site development in Ban Tai on Koh Phangan, rather than a name covering an established collection of projects. Its published scheme has four single-storey pool villas on a combined 920-square-metre site. Each one is planned with one bedroom, 101 square metres of built-up area and a 230-square-metre plot. The modest scale is central to the offering: a private home with its own pool, not a large resort estate.[1]

The project website identifies Dmitrii Gapii as its founder and developer and credits the architecture to Yura Lauri. Gapii describes building his own house in Kyiv with his father in 2016. That is a personal account of hands-on construction, not evidence of a completed portfolio of residential developments in Thailand. The published designs favour timber, stone and glazed tiles, with a pool for each home. Those design decisions are visible in the plans; actual materials and workmanship remain matters for the finished building and its specifications.

A villa purchase with two separate contractual relationships

The proposed land arrangement is a 30-year lease. Hush Villas says the advertised package includes the first three years of land rent, which leaves an important ongoing cost beyond the initial price. Keller Henson's project listing describes a lease signed directly with the landowner and a separate building contract with the contractor. It also says that the developer is not itself a party to either agreement. This is the agent's description, not an inspection of executed contracts. The Thai legal entities, counterparties and obligations for an individual villa are not identified in the public material reviewed.

The developer publishes a four-stage construction payment plan of 30%, 30%, 30% and 10%, linked to signing, structural completion, finishing and completion. For a buyer, the practical issue is who certifies each milestone and what happens if the work is late or incomplete. A land lease must also be considered on its own terms. Under Thailand's ordinary rules, leases exceeding three years need registration to be enforceable beyond that period, the standard maximum is 30 years, and a renewal promise is not the same as an automatic extension or ownership of the land.

One site, two advertised completion dates

The timing is not consistent across the material currently available. Hush Villas' own construction schedule ends with handover in the first quarter of 2027. Keller Henson lists the fourth quarter of 2027 instead. Right Way reported poured foundations and erected columns in its July 2026 site update, but that earlier update does not establish the present construction stage. Until a dated building update and the proposed contract align, neither advertised completion date should be treated as a verified commitment.

The USD 135,000 figure still shown on the developer's website was explicitly linked to a foundation-stage offer in the second quarter of 2026. It is not a confirmed November 2026 quotation. The same distinction applies to the site's rental-income and resale projections: they are promotional scenarios, not demonstrated outcomes. What is clear about Hush Villas is its specific four-home design and the people publicly associated with it; the exact legal and financial proposition depends on the lease, building contract and current offer for the chosen villa.

Sources

  1. Hush Villas · Home · 2026-11-20 · Home — four villas and leasehold marketing · Hush Villas markets a small four-villa development on Koh Phangan. The project site markets a land-lease structure for purchasers. (hushvillas.com)