Snag list, defect liability and warranty
A snag list records defects identified at inspection. It proves condition but does not by itself set repair timing, liability or retention. A defects-liability period, construction warranty, appliance warranty and latent defect are different rights with different scopes and timelines.
Navigation page: noindex, followLet’s explore this page together
Four layers of post-construction protection
The first layer is inspection and the snag list. The buyer compares the unit with the SPA, plan and specification and records location, description, severity, photograph and requested action. It should be signed or formally acknowledged by the seller; otherwise it remains unilateral evidence of condition.
The second layer is the contractual defects-liability period during which the seller must rectify defined defects under the SPA procedure. It may contain short notice periods, wear-and-tear exclusions and a separate route for urgent failures. Handover signature should not automatically be treated as waiver of latent defects where applicable law provides otherwise.
The third layer is the Construction Law. Article 71 sets minimum defect-warranty periods under a construction contract: ten years for specified structural systems, five years for external walls, windows, doors and roofs, and two years for electrical, plumbing, mechanical and related works [1]. A unit buyer should not automatically assume direct status under the construction contract; applicability, defendant and commencement require legal review. The fourth layer is manufacturer warranty for equipment and appliances.
What a snag list is confused with
A snag list is confused with a rectification agreement. A list without deadline, responsible party, access procedure and consequence does not ensure repair. A rectification schedule and closure record are required.
A cosmetic snag is confused with a latent or systemic defect. A scratch is visible at handover; leakage inside a wall may appear later; a common pipe belongs to the building even though damage is visible in the unit. Evidence and responsible parties differ.
Developer warranty is confused with manufacturer warranty. An air-conditioner may have brand coverage, installation may be a contractor issue, power supply a common-system issue and resulting damage an insurance event. One call to the sales representative does not route the claim correctly.
How to document a defect for closure
For each item record number, room, precise location, scaled photograph, description, specification reference, category, urgency, proposed action and deadline. “Poor finish” is difficult to verify. Building-service defects may require testing, readings or a specialist report.
Before handover, agree whether part of the final balance may be retained, who holds it, release conditions and dispute treatment. If there is no retention, the SPA should at least provide a repair deadline, reinspection, escalation and a right to use a third party with recovery of reasonable cost where performance fails.
Sign closure only after reinspection. Do not close a functional defect solely from a contractor photograph. Preserve list versions, correspondence, access dates, refusals and recurrence. A common-area problem should also be notified to the manager or building body.
Where the buyer loses evidence
The first mistake is signing clean acceptance based on an oral promise to repair later. After handover, the dispute shifts from an acknowledged snag to proof of when and by whom damage arose. Material items should appear in a signed annex.
The second is missing a short notice period. The contract may require visible defects to be reported within days. Even where longer rights exist, early recording materially improves evidence and separates construction failure from occupant damage.
The third is confusing rectification with an upgrade. Replacing an agreed material with a more expensive one may be an improvement rather than correction. The benchmark is the signed specification and required quality, not an impression created by a render.
Documents to check
- SPA specification and defect clause
- signed snag list
- rectification schedule
- construction and manufacturer warranties
- reinspection closure record
What this does not prove
- cause of defect
- legal liability of a particular party
- complete rectification
- direct applicability of construction warranty to the buyer
Frequently asked questions
Does a signed snag list guarantee rectification?
It is stronger evidence than oral discussion, but timing, procedure, responsibility and closure control are still needed.
Does the ten-year period apply to every crack?
No. The law distinguishes work categories, and applicability to the buyer and defect requires technical and legal review.
Sources1
- [1] Law on Construction — Kingdom of Cambodia — 02.11.2019
Sources are printed as text only. We do not publish outbound links.
Glossary material for orientation only. It is not legal, tax or investment advice; check a real transaction with a Cambodian lawyer.