Thailand News
Second Road resurfacing is underway through central Pattaya
Let’s explore this page together
A 3.35 km central corridor entered phased resurfacing
The scheme covers Second Road between the Wat Chai Mongkol intersection in South Pattaya and the Dolphin Roundabout in the north. Preparatory information released in late June described a 3.35 km project split into two main sections rather than one continuous closure.
The first active works started around the Central Pattaya intersection and moved north. In selected sections, crews were to remove and recycle part of the existing pavement structure before laying a new asphalt surface. Farther south, later inspections led the city to use an overlay approach where the underlying road was considered sound enough to retain.
The point is relevant because the road had already been affected by several years of drainage, water-pipe and underground utility works. Resurfacing was intended to restore the carriageway after those projects, but it did not instantly remove construction activity from the corridor.
Traffic stayed open while access shifted between work zones
The city said contractors would work on one side at a time and aim to keep at least one lane available in each direction. Businesses were also asked to keep vehicles away from roadside parking spaces so construction equipment could move through the active zone.
For residents and long-term renters, the practical issue was less about a citywide closure and more about uncertainty from block to block. A street could remain technically open while access to a building, parking space or usual turn became slower or temporarily awkward. Anyone comparing homes around Second Road therefore had a reason to look at the actual entrance and daily route, not just the distance shown on a map.
By August, the city was also telling contractors to control dust with regular watering, install traffic signs and coordinate with police and municipal officers. Those steps were meant to reduce disruption, not eliminate it.
The September target was a deadline, not proof of completion
Early reports described the construction period as roughly 90 days. Later city inspections referred to a more specific contractual target of September 17, 2026, with penalties possible for contractors who missed the deadline without a valid reason.
An August 20 progress update put the Central-to-North Pattaya section at about 50% complete and the South Pattaya-to-Central section at about 10%. Officials were pressing for faster work before the Pattaya Marathon scheduled for late September.
The reliable updates used for this article do not establish that the entire resurfacing project was in fact completed by September 17. The date should therefore be treated as the city's target, not as a confirmed finish date. For someone travelling through central Pattaya, the condition of the specific section remains more useful than assuming the whole corridor changed status at once.
Sources4
- Pattaya Mail — Pattaya aims to complete Second Road upgrade in 90 days — July 22, 2026.
- Pattaya Mail — Pattaya races to transform second road before September deadline — July 23, 2026.
- The Pattaya News — Pattaya Mayor Accelerates Second Road Improvements, Phase 2 Targeted for September 17th Completion Ahead of Marathon — August 20, 2026.
- The Pattaya News — Get Ready for a Major Road Project on Second Road in Pattaya! — June 30, 2026.