Three southern double-track railway sections receive construction approval

Nova Asia AI assistant

Let’s explore this page together

Event datePublished on NovAsia:

The approved corridor runs from Chumphon through Surat Thani and Hat Yai to Padang Besar at the Malaysian border. For residents and people considering a move to southern Thailand, the key point is the timeline: this is now an approved infrastructure programme, not a new rail service that can already be used when comparing daily journeys.

Construction approval covers three southern sections

The Chumphon–Surat Thani section has a budget of THB36.89232 billion. Surat Thani–Hat Yai Junction accounts for THB61.53455 billion, while Hat Yai Junction–Padang Besar is budgeted at THB8.37145 billion. Together they make up the THB106.79832 billion package approved by the Cabinet.

The work includes track and signalling upgrades intended to raise capacity for both passenger and freight trains. The southern end also extends the double-track corridor to Padang Besar, the rail border crossing with Malaysia, giving the project a cross-border freight and passenger dimension.

One previously discussed extension is not part of this construction approval. The Hat Yai–Songkhla section has been deferred while issues involving occupation of railway land are addressed, so the Cabinet decision should not automatically be taken as approval to build the full route previously proposed toward Songkhla.

Context and next steps

The timetable runs into the early 2030s

After Cabinet approval, the State Railway of Thailand still has to prepare tender documents, run procurement and award contracts. The agency has said it expects tendering and contract signing to take place in 2027.

The approved implementation periods are different for each section. Chumphon–Surat Thani runs through fiscal 2032, Surat Thani–Hat Yai Junction through 2033, and Hat Yai Junction–Padang Besar through 2031. Faster journeys, greater service frequency or improved freight capacity therefore remain intended outcomes of completed construction rather than benefits available today.

Someone choosing where to live in the South can treat the approval as useful long-range context. Current commuting, airport access and intercity travel still need to be judged against the transport network that is operating now.

**Three other Phase 2 routes still need a final Cabinet decision**

The same Cabinet meeting gave in-principle backing to Pak Nam Pho–Den Chai, Den Chai–Chiang Mai and Thanon Chira Junction–Ubon Ratchathani. Those projects were not cleared for construction on the same basis as the three southern sections.

The State Railway of Thailand was instructed to revisit feasibility, passenger and freight forecasts, marketing strategy and business plans before submitting the proposals again. The distinction matters because describing all six routes as fully approved for construction would overstate the decision taken on 1 September.

Sources3
  1. Royal Thai Government — Cabinet decision on Phase 2 double-track railway projects — 1 September 2026.
  2. Thailand Public Relations Department — Cabinet Approves Six Double-Track Railway Projects — 2 September 2026.
  3. The Nation — Cabinet approves THB106.8bn southern double-track rail plan — 1 September 2026.

Related guides