Kathu–Patong expressway timeline now runs to October 2031
Let’s explore this page together
The September 16 government update gives Phuket residents a clearer sense of how far away the project remains. It does not mean the expressway is ready to be built: the revised scheme still has to pass the next approval stage before the construction timetable can become operational.
Cabinet consideration comes before the construction schedule
The current plan is to take Phase 1 to Cabinet around December 2026. Subject to approval, land acquisition is targeted for completion by January 2027 and a contractor is expected to be selected around April.
Construction is scheduled to begin in October 2027 and run for about four years. Completion is targeted for September 2031, followed by an official opening in October 2031.
These dates are milestones in the government's present plan, not fixed delivery dates. Cabinet approval, inter-agency work, procurement and the construction programme all still sit between the project today and an operational road in 2031.
The tunnel design is still being adjusted
The latest version reduces the planned tunnel diameter from 17 metres to 14 metres, with the revised design still being circulated among relevant agencies. The Kathu and Patong interchanges are intended to connect the new route with the surrounding road network.
Government projections say the tunnel could reduce the Kathu–Patong journey to about five minutes once the expressway is operating, compared with roughly 30 minutes on the current route. That is a future operating estimate, not a travel time that residents can rely on today.
Phase 1 is also projected to carry around 50,000–60,000 vehicles a day, including motorcycles, after opening. As with the journey-time estimate, this is a forecast tied to the completed project.
**Housing decisions still depend on today's roads**
For people choosing where to live on Phuket over the next few years, the new timetable is useful mainly because it puts a date range around a long-running infrastructure plan. It does not remove the current congestion or change the practical commute between Kathu and Patong yet.
A renter or buyer making a decision now should therefore compare locations using the road network that exists today. The proposed five-minute tunnel trip may become relevant later, but treating it as a current neighbourhood benefit would overstate the project's status.
The same caution applies to property prices. A clearer infrastructure timetable can change expectations, but it does not by itself establish that a particular development or area will appreciate in value.