Thailand News
SRT brings Bangkok's Red Line Missing Link back into planning
Let’s explore this page together
The line would close a gap through central Bangkok
The scheme covers the Bang Sue–Phaya Thai–Makkasan–Hua Mak corridor and the Bang Sue–Hua Lamphong branch. SRT's published design totals 25.9 km, with about 22.4 km elevated and 3.5 km underground.
Its role is broader than adding another commuter service. The alignment is intended to remove at-grade conflicts between railway tracks and city streets along a corridor where trains still cut across busy roads. A fatal collision involving an SRT freight train and a bus at the Asok–Din Daeng crossing on May 16, 2026 brought that safety issue back into focus.
2034 is a planning target, not a construction commitment
SRT said in May that it planned to seek 2027 budget funding to update earlier studies and detailed design work. The agency was aiming to submit the project to Cabinet in 2028 and move toward procurement in 2029.
A July update still described the project as being revised, with 2034 retained as the intended service year. No later source reviewed for this handoff showed that construction had started or that the 2034 date had become binding. For residents or property buyers, the existing rail and road network therefore remains the relevant basis for today's commuting decisions.
Sources2
- The Nation Thailand — May 23, 2026.
- Prachachat Business — July 17, 2026.