Thailand News
Thailand revisits five regional transit schemes, with Hat Yai looking to 2035
Let’s explore this page together
Four published project plans point to openings in 2032–2034
Thailand's Mass Rapid Transit Authority is reviewing proposals for Chiang Mai, Phuket, Nakhon Ratchasima, Phitsanulok and Hat Yai in Songkhla province. MGR Online reported the authority's explanation at the MRTA Future Connect discussion on 17 October 2026. Updated assessments are intended to reflect urban development, travel habits, existing transport and weather conditions, all of which affect route design, likely ridership and affordable fares.
The authority's own project pages show a varied picture outside Hat Yai. Their timetables are planning assumptions, subject to the review and subsequent approvals.
| Location | Preparation described by MRTA | Planned opening year |
|---|---|---|
| Phuket | Feasibility review and preparation of the public-private partnership report | 2032 |
| Chiang Mai | Feasibility work and project design | 2032 |
| Nakhon Ratchasima | A project preparation consultancy contract has been signed | 2032 |
| Phitsanulok | Consultant procurement documents are prepared; further development awaits details and timing of the northern high-speed railway | 2034 |
There is consequently no common construction timetable for all five schemes. The review concerns how each system could work in its own city, including its relationship with transport already available.
Hat Yai's timetable starts with another study in 2027
Hat Yai's proposal predates this latest review. An MRTA statement published on 23 January 2026 described the Songkhla provincial administration's original concept: **12 stations over 12.54 kilometres**, connecting Khlong Wa junction with the minivan terminal via Kanchanawanit and Phet Kasem roads. Those specifications describe the earlier design and remain subject to reassessment.
The October reporting puts that earlier scheme's estimated cost at roughly **THB16.2 billion, excluding trains**. Thai Post and Thailand Construction describe possible changes, including sections at ground level outside the centre and better connections with Hat Yai railway station. The redesign would also take account of the severe flooding in 2025. A revised budget will depend on the work still to be done.
Thai Post's 17 October timeline places the study in **2027**, the request for project and investment-model approval in **2029**, construction in **2031** and opening in **2035**. These are provisional milestones, dependent on approvals and selection of a private partner. When the report appeared, the decree enabling MRTA to operate in Songkhla was still being enacted.
For someone taking a one-year lease in 2026 or 2027, the relevant journey is still the one possible today. The plans offer a view of potential urban development; current routes determine the time and cost of reaching work, school or the airport.
Sources5
- MGR Online — reporting on the five provincial transit projects discussed at MRTA Future Connect, 17 October 2026.
- MRTA — statement on joint discussions with the Department of Rail Transport and Songkhla authorities about the Hat Yai project, 23 January 2026.
- Thai Post — report on Hat Yai's proposed monorail timetable and design review, 17 October 2026.
- Thailand Construction and Engineering News — report on the proposed Hat Yai monorail and its provisional 2035 opening target, 18 October 2026; based on a Thai Enquirer post.
- MRTA — official project pages for Phuket, Chiang Mai, Nakhon Ratchasima and Phitsanulok, implementation plans and current-status sections, as available on 20 October 2026.