Kamala's flood response moves to a B50 million drainage proposal
Let’s explore this page together
A cost estimate is available, but approval has not been announced
The proposal followed an inspection of Phuket's flood damage by Deputy Transport Minister Sanphet Bunyamanee on 30 October 2026. Heavy rain from 26 to 29 October had affected roads and communities across the island. The inspection included officials from Phuket province, Kathu district and the Kamala local administration. The Phuket News reported the drainage proposal on 31 October.
According to the Thai government's 30 October statement, surveys and designs for drainage improvements in Kamala had already been prepared. The projected expense was capped at **B50 million**. Provincial officials were coordinating with the Department of Public Works and Town & Country Planning on a request for money from the central budget.
That is the project's financial position described in the 30–31 October reports. They do not identify an approved allocation, a signed construction contract or a date when the upgraded drainage system will be operating.
A bridge pier and narrow channels restrict the route to the sea
The problem is partly one of capacity. Officials said the channels carrying rainwater towards the sea were too narrow to cope with sustained heavy rainfall lasting two to three hours. A small existing highway bridge compounds the obstruction: one of its supporting piers stands in the watercourse.
The Department of Highways was therefore asked to examine a replacement bridge and develop a design allowing water to pass more freely. The Marine Department was also tasked with inspecting and dredging the downstream waterway to remove accumulated sediment. The published accounts do not establish whether the bridge replacement is included in the B50 million drainage estimate.
The bridge, downstream dredging and drainage design involve different pieces of work and more than one public agency. Their preparation does not confirm completion of the physical improvements. Any future benefit will also depend on which part of Kamala a household occupies and how its runoff connects to the improved sections.
For a long lease or purchase, an address-level assessment needs the site’s height relative to the street, the places where water collects and the availability of an access road during prolonged rain. A building may remain dry while the approach becomes impassable. Past flooding at that address helps establish the current exposure; an approved project map and implementation schedule would be needed to assess a specific reduction in risk from the proposed works.
Sources3
- Royal Thai Government, announcement on the Deputy Transport Minister's Phuket flood-damage inspection and Kamala drainage proposals, 30 October 2026.
- Thailand Public Relations Department, Phuket regional report on drainage and transport infrastructure assessments, 30 October 2026.
- The Phuket News, “B50mn drainage plan proposed for flood-hit Kamala”, 31 October 2026.