Pattaya sets out four-stage, 2.75-billion-baht flood drainage programme

Nova Asia AI assistant

Let’s explore this page together

News datePublished on NovAsia:

The council heard a plan for selected flood-prone areas

The discussion followed heavy September rainfall that left roads under water and caused flooding inside some homes. Mayor Poramet Ngampichet said the city had received approximately 2.75 billion baht in special budget support for a series of drainage improvements. He put the cost of a comprehensive citywide solution at around 21 billion baht, well beyond the resources currently available for this programme.

The smaller scheme therefore has defined geographic limits. City officials were preparing the terms of reference and contractor selection when the announcement was made. Reports of the meeting do not establish individual funding disbursements, signed construction contracts or firm completion dates for all four stages.

Context and next steps

Four stages cover roads from South Pattaya to Sukhumvit

The first two stages are scheduled for 2027–2029. One covers lower South Pattaya Road, Soi 18 off Pattaya Second Road and the lower section of Chaloem Phrakiat Road. The other addresses the upper stretches of Chaloem Phrakiat Road and South Pattaya Road. These are proposed work areas, not confirmation that construction has started.

Stages three and four have a 2028–2030 planning window. The third includes Sukhumvit Road, the railway parallel road and Land Office Road; the fourth covers the corridor between Sukhumvit Road and Sukhumvit Pattaya Soi 69, as well as Soi Kor Phai. The municipality describes the overall target area as approximately 15 square kilometres, taking in parts of South and Central Pattaya and the Thepprasit Road area.

Those overlapping schedules are important for anyone signing a long lease. Drainage construction could eventually improve access during storms, while excavation and traffic management may also affect everyday journeys. No street-by-street work timetable or traffic restrictions were confirmed in the reports of the announcement.

A higher rainfall target is not a guarantee for every building

According to the mayor's figures, the relevant drainage network currently copes with rainfall of roughly 70 millimetres per hour. The city's target after the upgrades is up to 130 millimetres per hour, with an estimated 37,300 households expected to benefit. The capacity and household estimates describe what the programme is intended to deliver. They have yet to be tested against the performance of completed works.

Officials said that the number of major flooding hotspots had previously fallen from 24 to around nine, with another three or four smaller trouble spots remaining. Locations mentioned included the railway parallel road near Soi Noen Phlap Wan, Pattaya Third Road and South Pattaya Road. Conditions can vary considerably within a single street, depending on drainage connections and ground levels.

Building drainage remains part of a long-term housing decision

Prospective tenants and owners can use the proposed road improvements to understand plans for a neighbourhood. Flood exposure at an individual address still calls for evidence about the building and its access. A ground-floor entrance, basement parking ramp or low-lying access road can remain vulnerable even where the surrounding main road is improved. Past flooding at the building and the condition of its own drainage system are still relevant, and the programme's delivery timetable should be revisited once contracts and construction schedules are confirmed.

Sources3
  1. Amarin TV, report on the Pattaya City Council meeting and four-stage drainage programme, 5 November 2026.
  2. Siamrath, report on Pattaya's 2.75-billion-baht flood mitigation programme, 5 November 2026.
  3. The Thaiger, “Pattaya unveils 2.75 billion baht plan to tackle chronic flooding”, 6 November 2026.

Related guides