Bangkok’s four proposed rail lines remain in preparation as two submissions target 2028

Nova Asia AI assistant

Let’s explore this page together

Event datePublished on NovAsia:

Four corridors, each at a preparatory stage

MRTA’s project pages describe a combined 64.8 kilometres of proposed railway across Greater Bangkok. The investment estimate reported in the October update is around 175 billion baht; it is a preliminary estimate, not a confirmed allocation of construction funding.

LineProposed corridorLengthStations
BrownKhae Rai — Lam Sali (Bueng Kum)22.1 km20
Grey, Phase 1Watcharaphon — Thong Lo16.3 km15
SilverBang Na — Suvarnabhumi19.7 km14
Light BlueDin Daeng — Sathon6.7 km9

These are planning parameters. MRTA is reviewing the Grey Line’s feasibility, while the Light Blue project requires studies and design work. The October report places Light Blue behind the Silver and Grey projects in the authority’s priorities.

For someone choosing a home, a proposed corridor provides context for the area’s longer-term development. The present transport network still determines whether the address works for the first year of a tenancy or for a move planned before the railway opens. Any expected improvement needs its own delivery timeline before it can become part of the daily commute.

Context and next steps

Land sharing and airport access shape the 2028 target

The Silver Line’s airport connection needs further work. MRTA is discussing access to the passenger terminal on Suvarnabhumi’s southern side with Airports of Thailand (AOT), while revisiting the design to reflect changes along the corridor. Detailed studies are expected to take about a year, with Cabinet submission targeted for 2028, according to the governor’s account reported by The Nation.

For the Brown Line, the same year represents a delay. The Nation’s 19 October report says submission has moved from the previous 2027 target because MRTA and the Expressway Authority of Thailand (EXAT) have yet to settle shared use of the corridor along Ngam Wong Wan and Prasert Manukit roads.

MRTA’s Brown Line page still displays a January 2026 schedule with Cabinet approval targeted for 2027. The later 2028 expectation comes from the October statement reported in the press. It does not establish a final construction or opening schedule, and a planned submission remains subject to subsequent government decisions.

Sources3
  1. The Nation — “MRTA’s 175-billion-baht rail plan targets two Cabinet submissions in 2028”, 19 October 2026.
  2. Bangkok Biz News — report on MRTA’s investment plans for four new rail corridors, October 2026.
  3. MRTA — official Brown, Grey, Silver and Light Blue project pages, consulted on 20 October 2026. The Brown Line page cites a schedule acknowledged by the MRTA board on 20 January 2026.