Cambodia puts EDC at the centre of its next EV charging expansion

Event date

The 170-plus figure measures permits, not live charging locations

On May 21, Mines and Energy Minister Keo Rottanak outlined a faster national rollout of charging infrastructure. Agence Kampuchea Presse reported the following day that the programme had an initial funding commitment of US$10 million and that more than 170 new charging-station permits had recently been approved.

That distinction matters for drivers trying to judge whether an EV is practical for their routine. Cambodia's regulatory framework separates permission to develop and construct a charging site from the conditions required before operation. A completed site must have an approved electricity supply, meet technical and safety standards, and pass the required inspection and certification process.

A permit therefore signals a project moving through the system; it does not confirm that a charger is switched on, publicly accessible or suitable for a particular vehicle. Route planning still depends on the actual location, connector, charging power and operating status of individual stations.

Highway power capacity is part of the plan

EDC's assignment goes beyond installing more chargers. The May announcement made stronger and more reliable electricity supply along major national highways an early priority, reflecting the fact that a charging network is limited by the grid behind it.

The ministry also instructed EDC to prepare a separate financing package for potential high-voltage charging facilities on corridors from Phnom Penh toward Preah Sihanouk province and Bavet. Heavy commercial vehicles are part of that longer-term requirement. Delivery vans, refrigerated trucks and eventually container trucks need substantially more charging power than a typical private car, which can require additional grid upgrades and transformers.

By July, the government had given a clearer indication of where the initial US$10 million package could be used. EDC was expected to support charging infrastructure in public spaces, recreation areas and tourism locations that private operators may not yet find commercially attractive. The public programme is therefore aimed partly at gaps in the market rather than simply duplicating private charging sites.

Drivers still need to judge the network one route at a time

The later July statement showed that the May announcement had moved beyond a single headline, but it did not turn every approved project into an operating charger. The expansion remains a combination of permits, grid work, public investment and private deployment, with different sites progressing at different speeds.

For an EV owner based in Phnom Penh, a denser urban network can make daily charging progressively easier. Intercity travel is a stricter test. A driver heading to the coast, a border city or another province needs usable charging at the right intervals and at sufficient power, not simply a large national total for permits or planned sites.

Sources

  • Agence Kampuchea Presse — “Minister of Mines and Energy Outlines EV Infrastructure Development Plan” — May 22, 2026.
  • Cambodia Ministry of Public Works and Transport / Fresh News — report on EDC's approximately US$10 million EV charging package — July 14, 2026.
  • Cambodia Ministry of Mines and Energy — Prakas on Principles and Procedures for Managing and Regulating the Development and Provision of Energy Supply Services for Electric Vehicles — February 20, 2025.