Show unit vs delivered property in Cambodia

Renders · showroom · specification annex · substitution · handover · updated July 2026

A show unit sells the feeling of the future apartment, but it is not always the contractual specification. If furniture, appliances, brands, ceiling height, materials or layout matter, put them in the SPA annex, signed specification or handover document, not only in the brochure.

Create an identity record for the show unit

Record the project, building, showroom floor or location, layout type, viewing date and finish-package name. State whether it matches the selected apartment's plan, orientation, area, height, windows, balcony and service points. Where it has no unit number, identify it as a non-unit display sample.

Ask the seller to list the differences in writing: oversized furniture, removed doors, mirrors, lighting, upgraded materials, appliances, decoration and items excluded from the price. An observation in the showroom belongs only to the identified sample and does not carry to the selected apartment without a link to the signed specification.

What Carries Weight

SourceUseRisk
RenderVisual idea of the projectNot delivered condition
Show unitSales sample and atmosphereStaging, upgrades and furniture package may differ
BrochureMarketing, layouts and general promiseMay include disclaimers and may not be contract evidence
Signed annexContract evidence for materials, area, brands and inclusionsDetails and substitutions must be checked
Handover recordActual acceptance of delivered unitLate to dispute if clean acceptance is signed without defects

What to Put in the Annex

Equivalent Substitution

A developer may want the right to replace a brand, model or material with an equivalent. The buyer needs to know who decides equivalence, whether refusal is possible, whether the price changes and what remedy applies if the delivered item does not match. This pass found no universal Cambodia-wide rule; it depends on the SPA.

At Handover

Compare the delivered unit against the signed annex, not memory of the showroom. If there are differences, record them in a defect list with photos, deadlines and responsible party before clean acceptance.

Handover has four different outcomes

For every item, distinguish: conforms to the signed specification; has a visible defect; is the wrong promised material, dimension or model; or could not be inspected because access, connection or safe conditions were unavailable. An uninspected area is not marked clear.

Cambodia's Civil Code requires the seller to deliver property conforming to the contract and expressly addresses a difference from a sample or model held out by the seller. The specific remedy still depends on the SPA, evidence and legal review. Record the location, photographs, required outcome, responsible party, deadline and effect on acceptance or final payment.

A visual handover does not confirm concealed systems

A light, tap or air conditioner working during the visit proves only momentary operation. It does not establish design capacity, wiring safety, concealed leakage, waterproofing, internal connections, fire-system integrity or structural quality. Do not open secured panels or apply force without permission and the relevant specialist.

RICS describes a home survey as visual, requires inaccessible areas and limitations to be identified, and observes services under normal operation without testing them. The standard is used here to define inspection limits. Refer a concern to the relevant engineer rather than closing it through an informal buyer test or a short video.

Close discrepancies through a separate evidence file

For every item, retain the contractual basis, original sample or claim, image of delivered work, notice date, seller response, agreed remedy, reinspection and closure evidence. Where the buyer accepts money or retains the difference, document that outcome without treating it as automatic acceptance of every other issue.

A clean handover, qualified handover, warranty claim and later rectification are different records. A concealed defect that appears later should not be treated as closed merely because it was not visible at handover; the applicable notice, time limits and remedies require review under the SPA and current law.

Seen a showroom? Send the brochure and SPA annex. We will help identify what is actually included and what remains a sales presentation.

Contact usTelegramTake the quiz

FAQ

Does a show unit automatically become the contractual specification?

No. We could not confirm a rule that a show unit automatically becomes the contractual specification for every purchase. Important items should be moved into the SPA annex, signed specification or handover document.

Can a brand or material be substituted with an equivalent?

Equivalent substitution is a contract issue. Check who decides equivalence, whether the buyer can refuse, whether price changes and what remedy applies if the delivered item does not match.

What should the unit be compared against at handover?

Compare the delivered unit against the signed annex, specification and handover records, not against memory of the showroom or a marketing render.

Sources

Brochure and price-list materials · the contract-clause library · defects and warranty materials · NovAsia comparison of the show unit and delivered property · checked July 7, 2026. A universal show-unit binding rule and a universal equivalent-substitution rule were not verified. This information is for general orientation and is not legal advice.

The show unit sells an idea; the contract defines delivery

A model apartment helps you understand the look and feel, but it does not guarantee every feature. Anything material should appear in the specification or contract.

AspectShow unitDelivered unit
FinishesPresentation-gradeContract specification
AreaVisual impressionDefined measurement basis
AppliancesNamed brandsListed brands or permitted substitute
ViewBest-case presentationYour exact unit exposure
FurnitureFully stagedOnly included package
TimingNot visibleContractual completion date