What is known
- PBG and SLF are distinct elements in the building-record system.
- TARUBALI digital maps do not replace official records.
- The agrarian and registration framework requires rights, holders and contractual roles to be distinguished.
In an off-plan project, you are not only buying a future asset. You are buying promises about the result, timing, records, parties and what happens if the promise is not performed. A render and construction schedule start the conversation; they are not evidence.
First turn the future asset into a verifiable description: where it will be, what will transfer, which specification and fit-out are promised, who must build and hand it over, what counts as a stage and what happens on change or delay.
Check six links: parcel ↔ future asset; contract party ↔ building obligation; PBG/planning ↔ stated project; stage ↔ independent evidence; payment ↔ concrete result; change or delay ↔ agreed consequences. If any link is absent, do not replace it with a ‘it will be ready’ promise.
A render does not define the subject of a transaction. A working description of the future asset needs the address and boundaries, asset type and number, plan, area and measurement method, rooms, finishes, furniture/equipment, common areas, parking, infrastructure and anything that affects the decision to buy. If an item ‘may change’, say so rather than hiding it in an attractive image.
You do not need to pretend to be an architect. Ask one simple question: can the future result be compared to this description at handover? If not, the agreement’s subject is not yet sufficiently defined.
The national agrarian framework distinguishes land rights and registration; PPAT is connected to deeds used for registration changes. This does not mean one document confirms a future project. It does mean that a future asset cannot be reviewed separately from the parcel, underlying right, current holder and the party undertaking to build or hand over the result.
Request a documentary map: who holds the underlying right, who is the contract party, who builds, who receives money and on what basis each role connects to the asset. If different people appear in the chain, the question is not whether that is ‘normal’ in general, but which records explain the connection here.
For an off-plan project, separate the planning layer for the address, building records and intended use after handover. Government Regulation No. 16 of 2021 connects building function and classification with PBG, SLF and SBKBG. SIMBG describes PBG and SLF as distinct system elements: one record should not be presented as the answer to every project question.
TARUBALI can help identify current planning documents and their status, but the portal expressly limits the role of digital maps and data. So ‘show the permit’ is too vague. Request a list of records, their reference details, their connection to the parcel and project, and the specific question each one is meant to answer.
Words such as ‘foundation’, ‘shell’, ‘70% complete’ or ‘handover soon’ are not one standard. Before signing, fix how a stage will be determined: what is included, who provides evidence, whether it can be reconciled with the asset and which records or inspection are required before the next payment.
SIMBG contains PBG/SLF-related processes and data, including construction and inspection sections in its applicant guidance. This does not give a buyer a ready report for a private project, but it confirms that construction and fitness are different stages requiring more than photographs.
A payment calendar is convenient for a seller, but a buyer also needs a trigger: which result has been achieved, what evidences it, who receives the amount and what follows if evidence is absent. For every sum, state whether it is price, deposit, service, processing or another item, and what you receive in return.
Government Regulation No. 34 of 2016 concerns certain rights-transfer events and related agreements. It does not set a safe off-plan payment schedule. It does remind us that contractual payment logic and legal/tax events should not be blended into one unexplained line.
In an off-plan project, not only the promised date and specification matter, but also the mechanism for changing them. What may change, who approves a change, how the buyer is told, how price or timing changes, what counts as delay and which options remain for the parties? If there is no answer, do not treat the stated date as a guarantee.
A useful review result is not predicting delay. It is removing ambiguity: which records prove a stage, what obligation rests on the contract party, when the buyer need not move to the next payment and what action sequence is fixed.
Collect the plan, specification, fit-out, boundaries and every point that affects the purchase decision.
Reconcile the underlying right, holder, contract party, builder and payee.
For every layer, request the address, record, reference details, status and the question it answers.
For every amount, state the trigger, evidence, payee and consequence if the result is absent.