Which date actually answers whether a project was delivered?

A condominium can have several accurate dates at the same time because those dates may describe different things. An early brochure or market report records what completion was expected to look like at that point; a later target may be a revision; topping out only tells you that the structural frame has reached its highest point. Pre-handover inspections, the first batch of keys, a phase handover and an occupancy certificate are separate milestones. A single “completion year” on a current listing therefore cannot reconstruct the history on its own.

The register keeps the precision of the original source. Pointer’s H1 2023 market report placed La Vista One in H1 2024 and Vue Aston in H2 2024. Those periods are useful historical records, but they are not buyer contracts and they should not be converted into invented day-level deadlines. Vue Aston later announced that Phase One handover had commenced in June 2024. That is a narrower event than the project-wide period shown in the market report.

La Vista One illustrates a different sequence. A developer update dated 15 November 2024 said the first batch of deliveries was expected in December, followed by a handover ceremony on 29 December. That establishes a real milestone, but the wording “first batch” does not establish that every unit or tower had been fully delivered at that point. Knight Frank later placed La Vista One River View and Vue Aston among developments handed over to buyers in H2 2025, so the two records cannot be treated as if they measure the same threshold without checking scope and methodology.

Royal Platinum provides a cleaner later-stage record. Hong Lai Huat’s 2024 annual report says the two residential towers were officially completed in July 2024 and that the development opened to the public in the same month. Pointer had earlier placed the project in H1 2024. Keeping those source periods as published is more defensible than manufacturing an exact number of late days from a half-year forecast.

The purpose of the register is therefore not to grade developers on punctuality. It shows what earlier evidence said, what later event can be documented, and whether those two points refer to a comparable part of the same development. Most of the stronger public chains are in Phnom Penh because the documentary trail is better there. They should be read as project histories, not as a national delay rate for Cambodia.

How documented dates and statuses changed across the reviewed projects

The first date is the earliest dated target that can be tied to the development in the sources used here; it is not necessarily a contractual deadline. The later milestone keeps the source’s actual scope, so the rows should not be read as a league table of delays.

Scenario 1 / 2

Earliest target

La Vista One
H1 2024 · market target
Vue Aston
H2 2024 · project in market report
Le Condé BKK1
Aug 2024 · dated secondary target
Time Square 306 / Time Square 5
H1 2025 · market target
Urban Village · Phase 2
H2 2025 · market target
Royal Platinum
H1 2024 · market target
Diamond Bay Garden
H2 2024 · project in market report
Scenario 2 / 2

Later milestone

La Vista One
First batch — Dec 2024
Vue Aston
Phase One handover — Jun 2024
Le Condé BKK1
Handover started — Mar 2025
Time Square 306 / Time Square 5
Handover — Dec 2025
Urban Village · Phase 2
Handover completed — 2025
Royal Platinum
Residential towers completed — Jul 2024
Diamond Bay Garden
Tower A: phased — late 2025–Q3 2026

Why apartment handover does not always mean the whole development is complete

Cambodian construction rules themselves distinguish occupation of an entire construction from occupation of only part of it. Articles 44–45 of the Law on Construction connect use of a construction that required a permit with an occupancy certificate and also allow temporary occupation of all or part of a construction under the prescribed conditions. Sub-Decree No. 226 makes the distinction more explicit: the final certificate follows completion of the whole construction, while a provisional certificate can cover a completed portion when the occupied and unfinished areas are appropriately separated.

That does not mean every development with residents inside must be operating under a provisional certificate. A project-specific conclusion requires the project’s own document. The legal framework matters because it shows why visible occupation, an opening event or a first key handover cannot by itself establish the status of the entire development. Likewise, the absence of a certificate from the public sources cited here is not evidence that no certificate exists.

Vue Aston is a clear example on the project side. The developer’s published milestone is explicitly Phase One handover commencing in June 2024. That date is meaningful for the units covered by that phase, yet it does not say that every remaining part of the development was complete in the same month. Knight Frank’s later H2 2025 market classification can therefore coexist with the earlier project announcement if the two sources are measuring different scopes.

Diamond Bay Garden makes the scope problem even more visible. Pointer’s historical market report placed the project in H2 2024, while the current developer timeline identifies 2026 as the target completion year for Tower A; secondary reporting also describes staged handover for that tower running from late 2025 into Q3 2026. Those records should not be collapsed into a single statement that “the project was delivered” until the relevant tower and milestone are clear.

For that reason, the register labels later evidence by what it actually proves: first batch, handover started, residential towers completed, or phased handover. A portal’s “ready to move” label and a consultant’s use of “completion” may still be useful, but they are not substitutes for scope. For an individual buyer, the strongest evidence is the document tied to the correct unit, tower or phase and the event that the contract treats as legally relevant.

Expectation and reality

Expectation

If a source says “completed,” the whole development must be legally complete.

Reality

First identify the event and the part of the development the source is describing.

TipA market classification is not a substitute for a project-specific legal document.

Expectation

Once handover starts, all units have been delivered.

Reality

Handover can be staged by batch, floor, tower or phase.

TipWording such as “first batch” or a named phase materially changes the meaning.

Expectation

If people are already living there, the whole development is complete.

Reality

The rules allow provisional occupation of a completed part when the required conditions are met.

TipThe status of a particular development still requires its own certificate or record.

Expectation

The date on today’s project page must have been the original target.

Reality

A current page may have been edited after the target changed.

TipThe historical target needs an older dated document or publication.

What can be said when the original date is missing or sources conflict

Different dates do not automatically mean that one source is wrong. The first test is whether the records refer to the same development, the same tower or phase, the same type of milestone and a comparable period. A developer can announce a first batch of keys while a consultant records the wider development as completed supply later. If the documents do not establish how those definitions connect, the responsible treatment is to show both with their scope intact.

La Vista One demonstrates why that matters. Pointer’s H1 2023 report placed the development in H1 2024 and listed 1,750 units; the developer’s current project page uses a different total, while Knight Frank later refers to La Vista One River View as an 875-unit development handed over in H2 2025. Between those records sits the developer’s own November 2024 announcement of a first batch due in December. The changing unit counts and labels are enough to rule out a simple “one correct date” interpretation for the entire development.

Vue Aston has a similar layered history. Pointer recorded H2 2024 as the expected completion period, the developer announced Phase One handover from June 2024, and Knight Frank later placed Vue Aston among projects handed over in H2 2025. Without the consultant’s inclusion rule for each phase, the H2 2025 entry cannot be treated as proof that the June 2024 phase milestone was false or that the same obligation was pushed back. The records become more useful when their different scopes remain visible.

For Le Condé BKK1, August 2024 appears in a dated secondary publication, but the cited public record contains no early primary contract or brochure establishing that month as a buyer-level deadline. Pointer’s H1 2023 market report, meanwhile, placed the project in H2 2025, so the early public record itself does not provide one uncontested expected period. Realestate.com.kh reported in November 2024 that construction was about 90% complete with handover expected in early 2025; a later roundup dates the start of handover to March 2025, while a current IPS listing gives 1 June 2025. Those later dates may represent different points in the handover process, yet that explanation should remain a possibility rather than a stated fact without a primary record. August 2024 appears in the table because it is the earliest target period located, but it is explicitly labelled as secondary evidence and not treated as a proven contractual deadline.

Diamond Bay Garden has an even less tidy chain. Pointer’s historical report placed the project in H2 2024, the current developer timeline shows 2026 as the target year for Tower A, and industry reports describe handover for that tower as staged across 2025–2026. The defensible result is an incomplete, tower-specific history, not a single completion date for the entire complex. The same rule applies whenever the original target cannot be documented: show the later milestone that can be supported and leave the delay calculation blank.

Resolve two dates that appear to conflict

1
Identify the scope

Match tower and phase

First establish that both documents cover the same part of the development.

2
Identify the event

Works, permission or keys

Compare the named milestones; initial handovers are not the same event as completion of the entire scheme.

3
Place it in time

Document date and event date

Keep the earlier target and later evidence separately instead of overwriting the history with the latest listing.

What a delivery-date history changes for a buyer

The public timeline is most useful as context for a buyer’s own contract. It can show whether today’s explanation matches older materials, whether a public target changed, and whether a reported handover covered the relevant tower or only an earlier phase. It does not rewrite the sale and purchase agreement or create identical rights for every owner in a development.

The buyer’s documents need to be read for the actual delivery date or period, any grace period, extension mechanism, definition of handover, and payments triggered by that event. Two purchasers in the same branded development may be tied to different towers or phases. A press release saying that “handover has started” does not eliminate those distinctions, especially when the event was only an inspection programme or a first batch of keys.

A documented date history becomes particularly useful when the schedule has changed more than once. An older dated publication gives the buyer a concrete reference point for asking what changed and which document now governs the relevant phase. A current project page is useful for the present plan, but it cannot prove that the same date was marketed one or two years earlier. Historical evidence and the live contract therefore serve different purposes.

A public revision also does not automatically create a right to compensation, termination or another remedy. The legal effect depends on the wording of the individual agreement, the applicable rules, the reason and mechanism for any extension, and the event the parties define as delivery. Cambodia’s Law on Construction confirms that commencement, completion and handover dates are important terms in construction contracts, but that general rule does not replace analysis of a purchaser’s own sale agreement.

For buyers who need to test the freshness of construction photos, trace an update to its original source or compare a progress report with the site’s actual condition, the separate construction-update guide covers that process. This page has a narrower job: keep the public sequence of promises and milestones intelligible, while leaving the buyer’s contractual position to the documents for the specific unit, tower and phase.

Document checklist

Complete0 of 4
ContractChecklist0 of 2
HandoverChecklist0 of 2

Questions about delivery dates and handover

Is the key-handover date the same as the project completion date?

Not necessarily. A key handover may cover a first batch, a single tower or one phase, while full-development completion is a broader milestone. The register therefore keeps the event label and scope instead of reducing everything to one “delivered” status.

Can part of a development be occupied before the whole project is complete?

Cambodian rules provide a mechanism for provisional occupation of a completed part under specified conditions and a provisional certificate. That is a general legal mechanism, not proof that any particular condominium is using it. The project’s own documentation is still required.

Does a revised delivery date prove that a developer is unreliable?

A single revision is not enough to rate a developer’s reliability. The more useful questions are what target was documented, how it changed, which phase it covered and what the buyer’s contract says. A broader project history may add context, but one schedule change is not a universal verdict on the company.

What should the register show if the original target cannot be found?

The original target should remain unknown, while a later documented milestone can still be shown. A current project page should not be used to reconstruct an earlier promise retrospectively. Without a comparable early date, a precise delay cannot be calculated responsibly.

What if two credible sources give different completion periods?

Start by comparing what the dates mean, not by choosing the more prestigious source: whole project or phase, start or end of handover, market classification or project document. If the difference remains unresolved, both periods can be retained with an explanation. Averaging the dates or selecting the more convenient one would hide the uncertainty.

Expert view

Elvira Shamuratova

The word “completed” is less useful than a date tied to a clearly identified tower, phase and event. A first batch of keys can be an important milestone without answering whether the rest of the development is finished. That distinction matters even more when a project has several towers or a staged handover. A market consultant may record a development as completed supply later than the developer’s first handover announcement. Both statements can coexist if they measure different thresholds. Treating them as interchangeable creates an artificial delay or an artificial on-time result. I would keep the public project history separate from the delivery date written into a buyer’s own sale and purchase agreement. The contract is where grace periods, extension rights and payment triggers become relevant to that buyer. Where the source trail does not establish the original target or the scope of a milestone, the register should preserve that uncertainty instead of manufacturing a precise verdict.

Elvira Shamuratova
NovAsia Cambodia expert
Expert profile →

Sources and check dates

Show sources and methodology5 checked sources
  • Law on Construction, Kingdom of Cambodia (2019)

    Articles 44–45 connect occupancy with certification and allow temporary occupation of all or part of a construction under the statutory conditions; Article 67 lists commencement, completion and handover dates among construction-contract terms. It is not used to establish the status of any particular development.

  • Sub-Decree No. 226 ANKr.BK on Conditions and Procedures for Granting, Suspending, and Revoking Certificate of Occupancy

    Articles 9–10 distinguish the final certificate after completion of the whole construction from a provisional certificate for a completed part when the conditions are met. The general rule does not prove that any development in the register holds a particular certificate.

  • Cambodia: Latest Construction News — DFDL

    Professional explanation of Sub-Decree No. 226, including final certification after completion and temporary certification for a built and safe portion. Used as secondary legal commentary, not as a substitute for the regulation itself.

  • Guideline on Construction Permit and Certificate of Occupancy — JBL Mekong summary of MLMUPC Guideline No. 291 DNS/KHTT

    The 6 July 2026 summary describes MLMUPC Guideline No. 291 DNS/KHTT dated 4 February 2026 and the current permit and occupancy-certificate procedure. The original guideline was not located in the accessible sources, so the summary is not treated as a substitute for the primary text.

  • Phnom Penh’s Real Estate Market Report — Pointer Research & Consultancy, H1 2023

    Dated market snapshot of expected completion periods: La Vista One H1 2024, Royal Platinum H1 2024, Diamond Bay Garden H2 2024, Vue Aston H2 2024, Time Square 306 H1 2025, and Urban Village Phase 2 and Le Condé BKK1 H2 2025. These are consultant expectations at the time, not buyer contractual deadlines.