Phuket Condo Supply and Delivery Pipeline
Published · Updated
Quick — 10-second read
The conclusion and the next practical check.
- Takeaway
- As of 27 September 2026, active construction can be confirmed for 13 Phuket condominium projects or separately scheduled phases. Twelve have usable unit totals adding up to at least 5,462 homes; one further large scheme is clearly being built but does not yet have a reliable single unit count for this comparison. A current completion or handover schedule is available for 10 of the 13.
- What to do
- For a specific project, give the latest dated construction update more weight than an old launch brochure, and check what the published date refers to. Build completion and buyer handover are different milestones.
What counts as an active condo project
The headline number includes only condominium projects or distinct phases with recent evidence of physical construction as of 27 September 2026. EIA approval, a permit, a sales launch or a contractor appointment can all happen before meaningful work starts on site, so none of them is enough on its own.
A phase is counted separately when it has its own unit total, timetable or project documentation. Several buildings sold under one project with one unit count and one delivery programme stay together; splitting them would risk counting the same homes twice.
For a buyer, four states matter: approved or selling but not yet proven active, visibly under construction, completed or in handover, and currently unclear. Only active construction feeds the main total. Completed projects, resale units, villas, hotels and remaining stock for sale are not treated as construction pipeline.
That makes the total deliberately conservative. When a project looks active in marketing but there is no fresh evidence from the site, leaving it outside the construction figure is more useful than inflating the number with an uncertain status.
Four statuses that should not be conflated
EIA / environmental approval
It supports project identity and the environmental review record. Approval alone does not show that physical construction is under way.
Construction permit
It shows that construction has been authorised under the permit. The site may still be inactive after the permit is issued.
Active construction
A recent dated source records real site activity such as piling, structure, MEP or architectural works. Only this state enters the headline total.
Completion / handover
Construction has finished or buyer handover has begun. Continued sales do not turn a completed development back into active construction.
How much active construction is documented
Active construction can be confirmed for 13 projects or separately scheduled phases as of 27 September 2026. Twelve have known unit totals adding up to 5,462 homes. Work is also clearly under way at one larger development, but a single reliable aggregate unit count is not available for the way this page compares projects. The useful headline is therefore “at least 5,462 units,” not a claim to the island’s full construction total.
Unit totals are available for 12 of the 13 projects, or roughly 92%. A current completion or handover schedule is available for 10 of 13, about 77%. In the remaining cases, an old target has expired, a replacement has not been published, or a multi-part development cannot sensibly be reduced to one date. That uncertainty is information in its own right.
At least four more schemes, totaling 2,112 residential units, are already announced, selling or supported by recent corporate material but do not yet have strong enough evidence of physical work on site. They are better viewed as near-term future supply than as homes already being built.
Adding those four to active construction gives a broader forward picture: 17 projects with at least 7,574 units of known size, plus one active scheme without a reliable aggregate unit count. That broader figure is useful for future supply, but it would overstate the answer to the narrower question, “What is actually under construction today?”
When documented active projects are currently due
2 projects · 552 units
Only active schemes with known unit totals and a current published schedule are included. One record distinguishes build completion from the subsequent buyer-handover milestone.
4 projects · 2,691 units
This is the largest block of projects with a current date. The timings are developer schedules, not guarantees that every unit will complete or hand over within the stated period.
3 projects · 1,022 units
The bucket uses the latest published schedule available for each project. Developers do not always use the same milestone: some publish construction completion, others a delivery or handover date.
1 project · 220 units
The developer supports a 2027 completion year, but a more precise current period is not supported at the same confidence level, so it remains outside the half-year buckets.
3 projects · 977 units + 1 unit count unknown
Construction is active, but two projects no longer have a usable current replacement for older dates. A third multi-part development cannot be reduced reliably to one delivery date and one aggregate unit count.
Why one completion date is not enough
Origin Place Centre Phuket shows how quickly a launch schedule can lose relevance. Early material pointed to a Q3 2025 construction start and Q1 2027 handover. On 29 July 2026, Origin itself said construction was instead due to begin in August 2026—almost a year behind the original start marker. Until a later update confirms actual work on site, the project is better treated as not yet proven active.
Two different dates do not always conflict. Arise Vibe’s progress page, updated 7 September 2026, still points to construction completion in Q3, while a corporate update mentions buyer handover in October. Those milestones can naturally follow one another: finishing the build and giving a buyer possession are not the same event.
The Title Heritage Bang-Tao illustrates a different grey area. The developer reported 98.7% progress in August, the original completion target had already passed, and current third-party pages disagree on whether the development is still under construction or already ready. Until that is resolved, it is more sensible not to count it as both active and completed.
When a published deadline has passed and no new official date exists, the old target should remain historical. Simply adding a few months and presenting the result as a new forecast would create a precision that the project information does not support.
Where active construction is concentrated
The table shows only projects with current evidence of active construction. Where a project’s aggregate unit count cannot yet be stated reliably, that gap is shown rather than filled by assumption.
| District | Projects | Known units |
|---|---|---|
| Mueang Phuket | 2 | 970 |
| Kathu | 1 | 862 |
| Thalang | 10 | 3,630 + 1 project without a unit total |
Where the pipeline still has gaps
The unknowns matter. One actively building development still lacks a reliable single unit total, and three of the 13 active projects do not have a current completion date that can be stated with confidence. An expired marketing date or a zero would make the table look tidier but less truthful.
Another 30 possible projects remain unclear for different reasons: some lack a sufficiently recent primary update from the site, some have new information that conflicts with an older status, and some have phase boundaries that could easily lead to double counting. That does not mean every one of those sites is inactive; it means they cannot yet support the same confidence as the headline total.
Projects near completion are particularly awkward. If a developer still reports near-complete progress while a current market page already calls the building ready, temporarily leaving it out of active construction is more defensible than counting it as both unfinished and complete.
The 5,462-unit figure is therefore not the whole future Phuket market. It is the part of current construction that can be supported confidently at the review date. Completed stock, resale units, villas, hotels and merely unsold apartments are different categories and are not added to it.
What the documented pipeline means for the next few years
Thalang currently carries most of the confirmed construction: 10 of the 13 active projects, 3,630 units with known totals, plus one active development without a comparable aggregate unit count. Mueang Phuket has two confirmed projects and 970 units, while Kathu has one project with 862.
On current published schedules, two projects representing 552 units are due to complete or move into handover during the rest of 2026. Another eight projects totaling 3,994 units sit in 2027. Those dates are plans, not a delivery forecast; phase sequencing can change, and construction completion may precede buyer handover by weeks or months.
Recent completions help put that timetable in perspective. CBRE reported only three Phuket condominium completions totaling 1,196 units in H1 2026 and noted delays or handover readiness issues at some developments. That number should not be added to current construction. Its value is simply to show why a developer’s target year is not the same thing as guaranteed finished supply.
REIC’s H1 2025 figures are broader again: 14,596 units in the surveyed Phuket market, 2,746 units of new supply and 12,135 units remaining for sale. Those measures describe market stock and sales conditions rather than physical construction. Combining them with the 5,462-unit active-construction figure would mix different questions.
Expert view

A launch-year handover promise becomes less useful once real construction data starts to accumulate. I would anchor a specific purchase to the latest dated progress update, then check whether the milestone refers to construction completion or buyer handover. Those dates can sit only weeks apart and still represent different stages of the transaction. An off-plan launch with no current site evidence therefore carries a different waiting risk from a project with documented work already underway.
Mark ErometskiyNovAsia Thailand expert
Expert profile →Sources and check dates
Show sources and methodology5 checked sources+
- Smart EIA Plus
Used to distinguish environmental approval from physical construction and to support project-document identity. EIA approval alone does not establish active site works.
- Explanation of Company’s Overall Operation for the Quarter 1 of 2026 — Rhom Bho Property Public Company Limited
The listed-company filing supports unit totals and Q1 2026 status for several The Title projects, including Modeva, Artrio, Katabello and Adora. Schemes shown as sales-only are not treated as active construction on the strength of this filing.
- The Modeva — The Title Residence
The developer page reports 75.3% construction progress for August 2026. It supports category-A status but does not guarantee a future handover date.
- The Title Artrio Bang-Tao — The Title Residence
The official project page documents that construction had started, but its displayed progress update is stale. The older completion target is therefore not treated as a current schedule.
- “Rhom Bho Property” Moves Forward Unstoppably, Laying the Foundation for Three New Projects After EIA Approval and Advancing Full-Scale Construction
Supports the physical construction start of Modeva, Artrio and Cielo after EIA approval. It is not sufficient to classify Cielo as active in late September 2026 because newer evidence points toward completion.
Useful next reading
A practical second opinion
Need to check a specific condo?
Send the unit link, price and your goal. We will separate the documented facts from the points that still need a unit-level check.
What to send: link, budget and target date